The Adare Bypass Design and Construction Contract was awarded to Sisk Sorensen Joint Venture in December 2024. Construction commenced in January 2025, and the contract completion is scheduled for June 2027 ahead of the Ryder Cup.

Construction works continue to maintain steady progress to achieve the June 2027 target completion date. The earthworks are substantially complete with reinstatement works now underway in the vicinity of all major structures. Topsoiling and finishing works continue to the road verges and attenuation ponds. Drainage and ducting works are also substantially complete across the site.

The majority of the precast deck units have been installed on the river Maigue bridge. All remaining structures are at the finishing stages, which include parapet installation, waterproofing and barrier installation. Pavement works are at an advanced stage, with both the lower and upper pavement layers now having been laid across large sections of the site.

Footpath works at the Adare and Croagh roundabouts are complete, with public lighting and signage installation also progressing well. The installation of environmental barriers and vehicle restraint systems continue to advance across the scheme. Landscaping planting has recommenced and will continue throughout the 2026/2027 planting season.

Overall, the project remains on schedule to be open for June 2027. Further information is available at www.adarebypass.ie